In case of ethane recovery, most of ethane is recovered from the stripping section of the dmethanizer with NGL. However, in case of ethane rejection some ethane is allowed to escape with the residue gas by warming up the demethanizer bottom. Decision whether to recover or reject ethane is made based on the prices of sales gas and ethane. If the price of sales gas is high and the price of ethane is low, then ethane rejection would be more economical.
There are many parameters that affect the economics of whether to fractionate at the plant site or not. Amongst the important parameters are the price of sales gas, the cost of transportation and storage of NGL and/or NGL products and fractionation cost of NGL at the hub.
In this study, HYSYS simulation of NGL fractionation units was carried out for typical shale gas composition. Three different flowrates (150, 200 and 250 MMSCFD) were considered and the cases were analyzed in both ethane recovery and ethane rejection modes. The estimation of total module cost, operating cost and the resulting economic feasibility was analyzed for both current product prices and other assumed reasonable prices.
The incremental economic analysis approach was utilized meaning, NGL market value was considered as a raw material cost for the case of fractionation. Further, it was assumed that the products are sold on site which eliminates the transportation and storage costs. For the gas composition considered and the current range of prices, the preliminary results are as follows. For the ethane recovery mode it would not be economical to fractionate the NGL at the plant site. However, in case of ethane rejection mode it is economical to fractionate the NGL at the gas processing plant.
See more of this Group/Topical: Fuels and Petrochemicals Division