480685 Managing Asset in Mature and Complex Facility by Developing Integrity Management Program Using Risk Based Approach

I Made Sukrajaya, Pertamina Hulu Energy Offshore North West Java, Jakarta, Indonesia and Margaretha Thaliharjanti, Engineering and Integrity, Pertamina Hulu Energy ONWJ, Jakarkta, Indonesia

Safe and reliable of facility is depend to the integrity or condition of its assets. PHE ONWJ (Pertamina Hulu Energi Offshore North West Java) has experience in managing its mature assets using their management system called Process Safety and Integrity Management (PSIM) System. The PSIM contains 12 Elements with 9 Sub Elements under Element 5 (Asset Integrity) as a core element. This paper will discuss the implementation of asset integrity element as one of PSIM system with risk based appoach in managing mature asset in PHE ONWJ.

The West Java facilities has 12 Offshore Complex Platforms (Flowstation), 4 ORF (Onshore Receiving Facility) and more than 200 Unmanned Platforms. Risk based approach method is necessary in managing mature and complex facilities to define prioritization of work program in order to achieve safe and reliable operation. This paper explains how PHE ONWJ defines risk of each asset then create overall asset execution program.

Focus of asset integrity program is the manned facilities (flowstations and ORF) and unmanned facilities with high production rate (NUI playground). The platform integrity status is given using traffic light category (green, yellow and red) which represent of the integrity status from piping, pressure vessel, pipeline riser and platform structural.

The risk based method is also used to define status of specific asset integrity, prioritize and evaluate overall work program that commonly known as the Inspection, Maintenance and Repair (IMR) program. The methodology of risk base approach is as follow :

- Selection the NUI playground asset

- determine consequences and likelihood of failure scenarios

- mapping risk profile by based on company’s integrated risk matrix

- screen asset based on high, medium and low risk

- create work program for high and medium risk

This method successfully reduces PHE ONWJ’s leak record each year as well as maintenance cost.