This paper discusses a dynamic simulation study to determine the relief loads for several hydro processing units of a major grass-root refinery. From the simulations, increasing temperature and decreasing pressure for each item of equipment was estimated as a function of time. These data were then analyzed to determine the peak mechanical stresses on the piping and exchangers during the entire event. Mechanical design conditions of the equipment were increased where necessary.
The second objective was to size the depressurization system which was designed to reduce the unit pressure to 50% of design pressure (or 100psig, whichever is lower) over a period of 15 minutes. The sizing took account of several cases such as power failure, reactor runaway etc.
Finally, the study estimated the stripper feed condition at different time points during the depressurization scenario. This was conducted to evaluate the column relief load in a situation where temperature is increasing, but flowrate is decreasing. The possibility of vapor breakthrough to the stripper from the separator during depressurization was also analyzed. In some cases this can be the controlling relief load for the downstream column, as the feed stream gets significantly more pre-heat when the upstream heat-sinks, such as the unit feed liquid, are lost.